Calculate Your Savings
The Standard OEE Calculation
(1)
Actual Production Time
=
Planned Production Time - Downtime
(2)
Planned Production
=
Actual Production Time * Parts Per Minute
(3)
Availability
=
Actual Production Time
Planned Production Time
(4)
Performance
=
Parts Produced
Planned Production
(5)
Quality
=
Good Quality Parts Produced
Parts Produced
Your OEE Calculation
This calculator aims to give you a rough idea of what your OEE percentage is at the moment. By comparing this to world Class OEE figures, you will get an idea of the
possible cost savings you can realise per day, per month and per annum.
(1)
Planned Production Time
=
0
minutes
(2)
Ideal Total Production Value
=
0
GBP
(3)
Actual Production Time
=
0
minutes
(4)
Planned Production
=
0
parts
(1)
Availability (World Class = 90.0 %)
=
0
%
GBP
0
(2)
Performance (World Class = 95.0 %)
=
0
%
GBP
0
(3)
Quality (World Class = 99.9 %)
=
0
%
GBP
0
(4)
OEE (World Class = 85.0 %)
=
0
%
GBP
0
Manually Update OEE Values